INDUSTRIAL SECTOR

Industrial Sector
Industrial Showcase

AURICO GOLD

ONTARIO, CANADA
This $115 million, multi-stage project required 400+ field personnel and over 530,000 man hours to complete. The total project scope and service delivery included supervision of the entire process, labour and equipment for the construction of a new gold mill concentrator and paste plant including plant internal structural steel, equipment installation, piping, electrical, instrumentation, controls, HVAC, insulation, steel fabrication, cladding, roofing, exterior doors and finishes, and plant commissioning. Following the successful completion of this project, the client rehired Stuart Olson for follow-up capital construction and due to our large project multi-services mining construction capabilities.

MINING CONSTRUCTION

BRITISH COLUMBIA, CANADA
This current British Columbia based capital project is valued at approximately $50 million and at completion will exceed 400,000 man hours utilizing a peak crew of 150 trade personnel. The scope of work includes the installation of approximately 200,000 sq. meters of roofing and wall cladding for industrial buildings. When this ground breaking project is complete, it will be one of the most environmentally responsible and sustainable mining and minerals processing facilities in operation globally.

OIL SANDS 260KV SUBSTATION

ALBERTA, CANADA
This $40 million project was successfully completed in 2013. The scope of work included the turnkey construction of new 260kV and 35kV sub-stations including: 9 km of power line complete; 34 tower structures; major highway crossing & utility crossings including existing 260kV and 25kV lines; with all tower base foundations were performed under difficult circumstances. The project required the supervision of 14 subcontractors, workface planning, detailed cost reporting and forecasting and pre-commissioning services. At its peak the project required 205 personnel and 266,500 man hours to completion.

MULTIPLE POTASH EXPANSIONS

SASKATCHEWAN, CANADA.
The expansion of the Saskatchewan potash industry resulted in the construction of multiple projects for several owners on multiple sites. With an ongoing value estimated at over $100 million, the completion of these projects is instrumental in expanding and modernizing the Saskatchewan potash production base. The scope of work included the supply and installation of mechanical insulation, HVAC and dust collection systems, building cladding, firestop as well as asbestos abatement. At peak, the projects required 150+ trade personnel and will exceed 1,000,000 man hours at completion.

CARBON CAPTURE - BOUNDARY DAM PROJECT

SASKATCHEWAN, CANADA
The Carbon Capture Project is the largest Carbon Capture facility in the world. This facility eliminates 1 million tons of CO2 emissions from the atmosphere each year. Stuart Olson was responsible for the excavations, forming, and pour­ing of the large foundations/piers/slabs (2,600 m3 total) for the compressor portion of the Carbon Capture process. We were also responsible for the excavations, forming and pouring of the transformer bases and the concrete encased underground conduit, which supplies power to the compressor area.

RIO TINTO ALCAN KITIMAT MODERNIZATION PROJECT

BRITISH COLUMBIA, CANADA
New Aluminum Smelter in Kitimat BC replacing ½ of the existing smelter which was built in 1954. Once completed it will be the most modernized environmentally friendly smelter in operation globally. Our $33M scope of work included all the buildings’ roofing and wall Cladding.

SHELL ALBIAN


From 2008-2010, NIICI completed the mechanical insulation on tanks & vessels, cladding, commissioning, valued at $25M.

SHERRITT INTERNATIONAL


Since 1991, we have be providing $3M/year maitenance services for insulation, cladding and asbestos removal.

CAMERON FALLS G.S. POWERHOUSE UPGRADES

ONTARIO, CANADA
Completed in 2013, this $1.6M 120/208V Power & Lighting upgrade consisted of; replacement of low voltage panels, UPS, transfer switches & cable feeders; replacement of all branch conduit & circuits; replacement of all emergency lighting & receptacles; replacement of all lighting with fluorescent, LED & induction lighting fixtures.

AURICO GOLD – BACKFILL PASTE PLANT ELECTRICAL & MECHANICAL

ONTARIO, CANADA
This $8.4M project consisted of installing a new Paste Backfill Plant for the existing mine. Stuart Olson provided the complete installation of equipment, piping, electrical, instrumentation, steel fabrication and erection.

ABB - NEW LISKEARD SOLAR FARM PROJECT


Project included installation of all underground cabling, wiring up of solar panels and combiner boxes as well as power distribution.